© Reuters. PG&E crew work on power lines to repair damage caused by the Camp Fire in Paradise,

By Jim Christie and Nichola Groom

(Reuters) – A major battery storage project that would help California replace three of its power plants may need to be scrapped as a result of PG&E Corp’s bankruptcy, according to court documents filed this week.

Californian electricity and gas supplier PG&E filed for bankruptcy protection in January, in anticipation of significant expected liabilities from wildfires in the state.

The bankruptcy poses a threat to California’s climate change ambitions by putting in limbo dozens of large solar, wind, and other clean energy projects PG&E has contracted with other companies.

Because PG&E can reject contracts in bankruptcy, energy developer esVolta LP said in papers filed with the U.S. Bankruptcy Court in San Francisco on Wednesday that it feared it would not be able to line up financing for its 75 megawatt Hummingbird battery storage project.

“Hummingbird’s position is becoming untenable,” esVolta said in the filing, noting PG&E had said it was not in a position to make a decision on whether to keep or reject its contract for using the planned battery-storage facility.

esVolta is one of four companies that received large battery storage contracts from PG&E last year as clean, cost-effective alternatives to three Calpine Corp natural gas generators in Northern California.

The others include Tesla Inc, Vistra Energy Corp unit Dynegy, and Micronoc Inc.

esVolta and PG&E did not immediately respond to requests for comment.

Tesla declined to comment on its contract, which is for a 182.5 MW project that would be owned by PG&E. Neither Dynegy nor Micronoc responded to requests for comment on their projects, which are for a 300 MW facility and 10 MW of storage, respectively. One megawatt is capable of powering about 750 homes at once.

The California Public Utilities Commission, which approved the contracts last year, said it had confidence that the Tesla, Dynegy and Micronoc contracts would progress.

“While it is unfortunate that they (esVolta) are unable to find necessary financing, the CPUC believes the other projects are able to continue with project development,” CPUC spokeswoman Terrie Prosper said in an email.

The market for energy storage is still small, but batteries have long held the promise of solving the intermittent nature of renewable energy sources such as wind and solar, so their development is closely watched by investors, regulators and power companies.

The Hummingbird storage facility was scheduled to begin construction in the second quarter of 2020.

Disclaimer: Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. All CFDs (stocks, indexes, futures) and Forex prices are not provided by exchanges but rather by market makers, and so prices may not be accurate and may differ from the actual market price, meaning prices are indicative and not appropriate for trading purposes. Therefore Fusion Media doesn`t bear any responsibility for any trading losses you might incur as a result of using this data.

Fusion Media or anyone involved with Fusion Media will not accept any liability for loss or damage as a result of reliance on the information including data, quotes, charts and buy/sell signals contained within this website. Please be fully informed regarding the risks and costs associated with trading the financial markets, it is one of the riskiest investment forms possible.